PROJECTS
 

Clitheroe Pumping Station
During construction Completed pumping station

Scope of Work

A. Electrical
• To supply one control panel to operate the two 1.5 kw submersible pumps
• All telemetry signals provided and wired back to the outstation.
• To carry out the electrical installation to the building
• Test and commission the system.

B. Mechanical
• To supply two Grundfos SVX-014 – B1 submersible pumps (EX rated), ladders and lifting beams
• To install all equipment
• Connect our rising main within the pre built valve chamber.
• Test and commission the system.

C. Minor Civil Works

D. Technical Support
• Method statements and risk assessments provided
• Post installation maintenance strategies up to local council adoption.